Build Up Rate Of Selected Items In The Built Industry

The information given below is to serve as guide to upcoming estimators in the built industry in Nigeria Thank you Abiodun Ayinde CONCRETE MATERIALS (DELIVERED TO SITE) CEMENT= 5.36*#1,700= #9,112.00 FINE AGGREGATE= .65*#5,416.67= #3,520.83 COARSE AGGREGATE= .85*#8,333.33= #7,083.33 MATERIALS TOTAL= #19,716.16 LABOUR/m3 LABOUR= #4,500.00 SUBTOTAL= 19,716.16+4500= #24,216.16 ADD OH/PROFIT (30%)= #24,216.16*30%= #7,264.85 TOTAL= #24,216.16+ #7,264.85= 31,481.00 NB: WATER WASN'T INCLUDED BECAUSE IT HAS BEEN INCLUDED IN THE PRELIMINARY   REINFORCEMENT MATERIAL (DELIVERED TO SITE) COST PER TONNE= #157,000 ADD: WASTE 5%= #157,000*5%= #7,850.00 BINDING WIRE= #6,000.00/2= #3,000.00 MATERIALS COST= #157,000.00+#7850+3000= #167,850.00 TRANSPORTATION COST= #12,000.00 TOTAL COST OF MATERIALS= 167,850.00+12,000.00= #179,850.00 LABOU