Build Up Rate Of Selected Items In The Built Industry
The information given below is to serve as guide to upcoming estimators in the built industry in Nigeria Thank you Abiodun Ayinde CONCRETE |
MATERIALS (DELIVERED TO SITE) |
CEMENT= 5.36*#1,700= #9,112.00 |
FINE AGGREGATE= .65*#5,416.67= #3,520.83 |
COARSE AGGREGATE= .85*#8,333.33= #7,083.33 |
MATERIALS TOTAL= #19,716.16 |
LABOUR/m3 |
LABOUR= #4,500.00 |
SUBTOTAL= 19,716.16+4500= #24,216.16 |
ADD |
OH/PROFIT (30%)= #24,216.16*30%= #7,264.85 |
TOTAL= #24,216.16+ #7,264.85= 31,481.00 |
NB: WATER WASN'T INCLUDED BECAUSE IT HAS BEEN INCLUDED IN THE PRELIMINARY |
REINFORCEMENT |
MATERIAL (DELIVERED TO SITE) |
COST PER TONNE= #157,000 |
ADD: WASTE 5%= #157,000*5%= #7,850.00 |
BINDING WIRE= #6,000.00/2= #3,000.00 |
MATERIALS COST= #157,000.00+#7850+3000= #167,850.00 |
TRANSPORTATION COST= #12,000.00 |
TOTAL COST OF MATERIALS= 167,850.00+12,000.00= #179,850.00 |
LABOUR/TONNE= #20,000.00 |
SUMMATION= #179,850 + #20,000.00= #199,850.00 |
ADD |
OH/PROFIT (30%)= 199,850.00*30%=# 59,955.00 |
TOTAL= 199,850 + 59,955= #259,805.00 |
FORMWORK |
MATERIALS |
MARINE PLYWOOD (19MM THICK SIZE 1.2*2.4) |
COST PER M2= #4,000 |
TRANSPORT PER ONE= #500 |
SUBTOTAL= #4,500/2.88= 1,562.5 |
ADD WASTE (5%) = 1,562.5*5%= #78.13 |
1,562.5+78.13= #1,640.63 |
PLANK/STRUTS= 10% OF PLYWOOD= 10%*1640.63= #164.06 |
TOTAL MATERIALS COST= #1,640.63+164.06= #1,804.69/M2 |
COST OF LABOUR/M2= 25% OF MATERIALS COST |
25%*1,804.69= #451.17 |
TOOLS= 5% OF MATERIALS COST |
5%*1,804.69= #90.24 |
SUMMATION= (1,804.69+451.17+90.24)= #2,346.10 |
ADD: |
OH/PROFIT= 2346.1*30%= #703.83 |
TOTAL= 2,346.10+703.83= #3,049.93 |
NUMBER OF USE=2 |
COST PER M2= 3,049.93/2= #1,524.96 |
PAINTING |
MATERIALS |
BERGER PAINT |
COST PER 20LITRES= #15,000.00 |
TRANSPORTATION= #1000.00 |
SUBTOTAL= #16,000/75M2= 213.33 |
2 COATS= 2*213.33= #426.67 |
UNDERCOAT= #3,000.00/20= 150 |
PAINT COST= 426.67+150= 576.67 |
LABOUR PER M2= #150.00 |
SUMMATION= 576.67+150= 726.67 |
ADD: |
OH/PROFIT (30%)= 726.67*30%= #218.00 |
TOTAL= #726.67 + #218.00= #944.67 |
TILES |
MATERIALS |
PRIME COST= #3,000.00 |
ADD WASTE (5%)= 5%*3,000 = #150 |
TRANSPORTATION = #200/M2 |
LOADING AND UNLOADING = 2*#50= #100 |
GLUE = 150/M2 |
SUMMATION=3000+150+200+100+150= 3600 |
LABOUR PER M2= #400.00 |
SUBTOTAL= #3,600 + #400= #4,000 |
ADD: |
OH/PROFIT (20%)= #4,000*20%= #800 |
TOTAL= #4,000.00 + #800= #4,800 |
CEILING |
MATERIALS |
15MM THICK HUMIDITY RESISTANT PLASTER BOARD SIZE 1.2*3M |
COST PER SHEET= #4,500 |
COST PER M2 = #4,500/3.6= #1,250.00 |
ADD WASTE (10%) = #1,250*10%= #125 |
BOARD COST= #1,250 + #125= #1,375 |
TRANSPORTATION= #1000/3.6 = #277.78 |
LABOUR PER M2= 30% OF BOARD COST |
30%* #1,375= #412.50 |
SUMMATION= #1,375 +#277.78 + #412.50= #2,065.28 |
ORDINARY POP PAINT COST= #3,300.00/ 20LITRES |
POP PLASTER = #3,100.00 PER BAG |
THEREFORE, #3,300.00 + (2*#3,100) = #9,500.00/40= #237.50 |
237.5*2= #475 |
LABOUR PER M2= #150 |
SUMMATION= #475 + #150= #625 |
COLLECTION= BOARD + SCREEDING |
#2,065.28 + #625= #2,690.28 |
ADD: |
OH/PROFIT (30%) = #2,690.28*30%= #807.08 |
TOTAL = #2,690.28 + #807.08= #3,497.36 |
ROCKWOOL |
MATERIALS |
35MM THICK |
MATERIAL (1*5M) COST = #10,000 |
TRANSPORTATION =#1,000 |
SUMMATION = #10,000.00 + #1,000.00 = #11,000.00/5M2 |
#2,200.00 |
LABOUR PER M2= #500 |
COLLECTION = #2,200 + #500 = #2,700.00 |
ADD: |
OH/PROFIT (30%)= #2,700*30%= #810 |
TOTAL= #2,700.00 + #810.00= #3,510.00 |
WALL |
RENDERING (1:4 MIX) |
CEMENT= 1*1700*28.8=#48,960.00 |
PLASTER SAND = (4*#12,000.00)/3 =#16,000.00 |
MATERIALS COST = #64,960.00/5 = #12,992 |
ADD WASTE/SHRINKAGE (15%)= 15%*#12,992= #1,948.80 |
SUBTOTAL= #12,992 + #1,948.80= #14,940.80 |
(#14,940.80*25)1000= #373.52/M2 |
LABOUR PER M2= #550 |
COLLECTION = #373.52+#550.00= #932.52 |
ADD: |
OH/PROFIT (30%)= 30%*#932.52= #277.06 |
TOTAL= #932.52+ #277.06= #1,209.58 |
FELTING |
MATERIALS |
SCUDOPLAST 4.5TNT MINERALS (0.9*10M) |
CLEANING AND PRIMING OF SURFACE = #400/M2 |
4.5TNT MINERALS= #21,600/9M2= #2,400.00 |
ADD WASTE (7.5%)= 7.5%*#2,400.00= #180.00 |
TRANSPORTATION PER M2= #600.00 |
COLLECTION = #400+#2,400+#180+#600 = #3,580 |
LABOUR PER M2= #620 |
SUBTOTAL= #3,580+#620= #4,200.00 |
ADD: |
OH/PROFIT (25%) =25%*#4,200.00 = #1,050.00 |
TOTAL = #4,200.00 + #1,050 = #5,250.00 |
Comments
I am lost in two areas in this rate breakdown
First is where the quantity per cu.m of concrete is 5.36
Second is where the plaster sand us divided by 3
I look forward to hearing from you soonest
Thank